Cost of direct labor $20 per hour
Cost of materials $43.75 per batch of 25 booklets
Cost of overhead items 50% of direct labor cost
Desired profit 20% of total manufacturing cost
Doc also finds out that
(1) They should use a 75% learning curve for estimating the cost of direct labor,
(2) The time to complete the 15tbooklet is estimated at 0.60 hour, and (3) the estimated time to complete the 25th booklet should be used as their standard time for the purpose of determining the unit selling price. What would Randy and Doc’s estimate be for the unit selling price?