Table 11.8
|
Activity |
Total Budgeted Cost |
Percent of Completion |
Value of work Completed ($) |
Actual Cost ($) |
Activity Difference ($) |
|
A B C D E F G H |
22,000 30,000 26,000 48,000 56,000 30,000 80,000 16,000 |
100 100 100 10 20 20 0 0 |
22,000 30,000 26,000 4,800 11,200 6,000 0 0 |
20,000 36,000 26,000 6,000 20,000 4,000 0 0 |
-2,000 6,000 0 1,200 8,800 -2,000 0 0 |
|
Total 100,000 |
112,000 |
12,000 Overrun |
And activity F is 20% completed with an incurred cost of $4,000.
Activities G and H have not been started. Is the air pollution
project on schedule? What is the valve of work completed? Are there
any cost overruns?
The value of work completed, or the budgeted cost to date for
any activity, can be computed as follows:
Value of work completed = (Percentage of work completed) *
(Total activity Budget)
The air pollution project discussed in the chapter has
progressed over the past several weeks, and it is now the end of
week 8. Lester Harky would like to know the value of the work
completed, the amount of any cost overruns or underruns for the
project, and the extent to which the project is ahead of or behind
schedule by developing a table like Table 11.8. The revised cost
figures are shown in the following table:
|
Activity |
Percent of Completion |
Actual Cost ($) |
|
A |
100 |
20,000 |
|
B |
100 |
36,000 |
|
C |
100 |
26,000 |
|
D |
100 |
44,000 |
|
E |
50 |
25,000 |
|
F |
60 |
15,000 |
|
G |
10 |
5,000 |
|
H |
10 |
1,000 |