charts
1.
Consider the following constraints
from a linear programming problem:
2X + Y 200
X + 2Y 200
X, Y 0
If these are the only constraints,
which of the following points (X,Y) cannot be the optimal solution?
• (0,
0)
• (0,
200)
• (0,100)
• (100,
0)
• (66.67,
66.67)
• •
• • •
• • •
• • •
• • •
2.
Activity Immediate
Predecessor Time ES EF LS LF
A — 4 0 4 6 10
B —- 5 0 5 0 5
C A 3 4 7 10 13
D B 8 5 13 5 13
E B 2 5 7 16 18
F C,D 3 13 16 15 18
G C,D 7 13 20 13 20
H E,F 2 16 18 18 20
How long could activity E be
delayed without delaying the completion of the project?
7
16
11
18
None of these
3.
According to above table, there
are five activities in a PERT project. If the normal distribution were used to
find the probability of finishing this project in 24 weeks or fewer, what mean
and variance would be used?
20 and 4.222
30 and 5.222
20 and 5.222
30 and 4.222
22.667 and 1.111
4.
Time in weeks:
According to above table, there
are four activities in the project. Assume the normal distribution is
appropriate to use to determine the probability of finishing by a particular
time. What is the probability that the project is finished in 16 weeks or
fewer? (Round to two decimals.)
0.07
0.93
0.43
0.77
None of these
5.
Over a 10-day period, the total
number of complaints was 360. The company wishes to develop a control chart for
the number of complaints. What would the upper control limit on the number of
complaints per day be for a 3 sigma (99.7%) control chart?
A. 12
B. 42
C. 48
D. 54
E. None
of these
6.
The overall average for the
samples is 36 ounces. Each sample contains eight bags. The average range is 1.3
ounces. The lower control chart limit for the sample averages would be
36.3730.
36.4849.
35.6270.
35.5150.
None of these
7.
The c-chart is be useful when we
take a number of measurements and
compute the average.
take a number of measurements and
compute the ranges.
find the fraction of the
production lot defective.
find the number of defective items
in a production lot.
None of these
8. A quality control program is
being developed for batteries. The percent defective for these in the past has
been 3%. If a sample size of 120 is taken, what would the 99.7% upper control
chart limit be?
0.0812
0.0767
0.0611
0.0307
0.0471