transportation problem in construction material

by | Nov 30, 2023 | questions

1.A
general contractor A, who is engaged in the construction of civil works, has
got projects at four different parts of Ethiopia that require cement for the
execution of the projects. The cement required for these projects are obtained
from the three factories located at different parts of the country. The demand
of OPC cement for each project site is 1100 qtls, 1200qtls, 800qtls and 1400
qtls for projects 1 to 4 respectively. The contractor is able to obtain 2000
qtls, 1500 qtls and 1000 qtls of OPC cement from factories of F1 to F3
respectively.

Table 2: Distance of project sites from factories

NB:
A-Asphalt Road Length in km, G-Gravel Road Length in km

Factories

P1

P2

P3

P4

F1

A

600

A

800

A

900

A

700

G

400

G

400

G

600

G

300

F2

A

200

A

200

A

200

A

100

G

300

G

400

G

500

G

300

F3

A

500

A

1000

A

450

A

700

G

300

G

300

G

450

G

400

The unit
cost of OPC cement at the three factories is equal. However; transportation
cost varies

depending
on the distance and road condition. The distance of the factories from each
project site

in
Kilometer is shown in table 2. The length of each road is divided into its
asphalt and gravel

component.

The
unit transportation cost of cement is 10 cents/qtl*Km for gravel road and 5
cents/qtl*Km for

asphalt road

From the above
given information;

a.
Calculate the unit transportation cost of cement
to each project sites from the factories and find the starting feasible
solution with the use of Matrix minima method

b.
Find the least total transportation cost of the
contractor that he should spend in transporting cements from factories to all
his project sites.

c.
If the transporters have decided to change the
unit transportation cost of cement at F1 and F2 by 5 % and 3 % more than that of F3 respectively, show the allocated quantities of
cement to each project that minimizes the total project cost.

Attachments:


ScholarMatic: Explanation & Answer

Your ready answer from a verified tutor is just a click away for as little as $14.99


  

Click Order Now to get 100% Original Answer Customized to your instructions!

HOME TO CERTIFIED WRITERS

Why Place An Order With Us?

  • Certified Editors
  • 24/7 Customer Support
  • Profesional Research
  • Easy to Use System Interface
  • Student Friendly Pricing

Have a similar question?

PLAGIRAISM FREE PAPERS

All papers we provide are well-researched, properly formatted and cited.

TOP QUALITY

All papers we provide are well-researched, properly formatted and cited.

HIGHLY SECURED

All papers we provide are well-researched, properly formatted and cited.

ScholarMatic: Get Started

Assignment Writing Service

Feel safe and secure when placing an order on our portal!
Fruitful cooperation begins with solid guarantees, and we are professional enough to promise perfect results. Let’s get it started!