Question #2
Please create the following Excel solution and answer in text
boxes inside Excel.
Jordan Enterprises is the largest maker and distributor of
smartphones in the world, and is planning its production for next
year. Jordan’s monthly demand forecasts are shown in the following
table:
| Month | Demand (Thousands) |
| January | 1100 |
| February | 1200 |
| March | 1050 |
| April | 1200 |
| May | 1400 |
| June | 1200 |
| July | 1000 |
| August | 800 |
| September | 1200 |
| October | 1600 |
| November | 1800 |
| December | 1300 |
Jordan’s production is hand-assembly, which is labor intensive,
and represents the largest limiting factor in its production
capacity. Component costs for each smartphone are $20 per unit. The
facility works 8 hours per day, 20 days per month. Each worker can
assemble a smartphone in 12 minutes, on average, and are paid $25
per hour, with the usual time-and-a-half pay for overtime work.
Jordan currently employs 1,500 production workers.
Jordan’s inventory holding costs are $5 per smartphone per
month, and is starting off with an inventory of 50,000 smartphones,
which is what the ending inventory must be as well. Overtime cannot
exceed 20 hours per month per employee, and there is a policy that
there can be no layoffs of employees.
#1 What is the optimum production schedule, if we assume that
there can be no hires, no backlogs, and no subcontracting? What is
the cost of this schedule?
#2 Does it help with the schedule in question 1 above if
we increase the overtime limit to 35 hours per employee per
month?