6)
The following information is provided for preparing a cash budget:
Beginning cash balance: $2,800
Cash receipts: $56,000
Cash payments: $41,000
Minimum cash balance: $2,000
Loan repayments: $10,000
What is the budgeted ending cash balance for this period?
7 Points
- $15,800
- $ 5,000
- $ 7,800
- $ 5,800
7)
The price variance indicates:
7 Points
- the difference between actual and standard hourly rate multiplied by the inputs planned.
- the difference between actual and standard hourly rate multiplied by the inputs used.
- the difference between actual and standard unit price multiplied by the inputs planned.
- the difference between actual and standard unit price multiplied by the inputs used.
8)
Efficiency variances help management by:
7 Points
- providing specific signals that corrective action needs to be taken.
- enhancing operational controls.
- providing improved measures of management efficiency.
- All of the answers are correct.
Saved
9)
A focus on continuous short-term reductions in manufacturing costs is called:
7 Points
- ideal standards
- variance analysis
- target costing
- Kaizen costing
10)
The materials usage variance should be calculated:
7 Points
- based on material purchased.
- only when there is an unfavorable variance involved.
- based on the difference between actual and standard price per unit multiplied by the actual quantity used.
- based on the amount of materials used in production.
11)
1Southern Company is manufacturing 5,000 units for the period. The following are actual and standard direct materials information:
Standard Costs: 1.5 pounds per unit; purchase price is $0.78 per pound
Actual Costs: 8,000 pounds purchased and used; purchase price is $0.75 per pound
Based on the information, the materials price variance is:
7 Points
- $390 Unfavorable.
- $390 Favorable.
- $240 Unfavorable.
- $240 Favorable.
12)
12. Southern Company is manufacturing 5,000 units for the period. The following are actual and standard direct labor information:
Standard Costs: 2.5 hours per unit; Hourly rate is $20.25 per hour
Actual Costs: 13,000 actual hours worked; Hourly rate is $19.75 per hour
Based on the information, the direct labor rate variance is:
7 Points
- $6,500 Unfavorable.
- $10,125 Unfavorable.
- $6,500 Favorable.
- $10,125 Favorable.