IST 7060 – Earned Value Exercise

by | Dec 1, 2023 | Posted Questions

Earned Value Exercise

Complete the following problems:

1. The
following project is at the end of its first week. Find the cost and schedule
variances, the cost performance index, the schedule performance index and the
estimate at completion.

Task Predecessors Duration in days Planned Value ($) Actual
Cost ($) Percent Complete

A None 2 500 650 100

B None 3 1000 1500 100

C A 2 200 300 50

D A 5 600 600 20

E B ,C 6 1200 550 10

To do this exercise, it is best to start with a Gantt chart
depicting the task relationships.

CV ______________________
CPI ________________

SV ______________________ SPI ________________

EAC _____________________

2. Using the
following information, calculate the cost performance index and the schedule
performance index. Then calculate the estimate at c

Planned value: 6700

Earned value: 6100

Actual costs: 7300

Budget at completion: 38900

CPI _______________________ SPI _____________________________

EAC ______________________

3. The
following project is at the end of its third week. Find the cost and schedule
variances, the cost performance index, the schedule performance index and the
estimate at completion.

Task Predecessors Duration in days Planned Value ($) Actual
Cost ($) Percent Complete

A None 3 600 650 100

B A 5 1000 1500 100

C A 2 200 300 100

D A 5 1000 600 100

E B ,C 6 1200 1200 100

F C 10 10000 12000 75

G F 7 700 0 0

H G 8 1600 0 0

To do this exercise, it is best to start with a Gantt chart
depicting the task relationships.

CV ______________________
CPI ________________

SV ______________________ SPI ________________

EAC _____________________

4. Mary is
the project manager for a web design project for Newberry Pet Foods. So far in
the six weeks (of the twelve week project), Mary’s team has completed five
tasks which had a combined planned value of $7800. However, the team spent
$8200 to complete those tasks. She has five additional tasks to complete the
project. What are the PV, EV, AC, CV,
SV, CPI, and SPI for Mary’s project?

5. Consider
the following information:

PV=6500

EV=5000

AC=7200

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________

ScholarMatic: Explanation & Answer

Your ready answer from a verified tutor is just a click away for as little as $14.99


  

Click Order Now to get 100% Original Answer Customized to your instructions!

HOME TO CERTIFIED WRITERS

Why Place An Order With Us?

  • Certified Editors
  • 24/7 Customer Support
  • Profesional Research
  • Easy to Use System Interface
  • Student Friendly Pricing

Have a similar question?

PLAGIRAISM FREE PAPERS

All papers we provide are well-researched, properly formatted and cited.

TOP QUALITY

All papers we provide are well-researched, properly formatted and cited.

HIGHLY SECURED

All papers we provide are well-researched, properly formatted and cited.

ScholarMatic: Get Started

Assignment Writing Service

Feel safe and secure when placing an order on our portal!
Fruitful cooperation begins with solid guarantees, and we are professional enough to promise perfect results. Let’s get it started!