normal critical path
Activity Normal time Crash time Normal cost Crash
cost
1-2 3 2 1000 1500
2-3 4 2 2000 4000
2-4 4 3 2500 3500
3-5 3 1 1500 2500
4-5 4 2 6000 12000
5-6 6 3 2000 5000
Determine:
a) Normal
critical path.
b) Crash
critical path.
c) The first
and last activities to be crashed.
d) Minimum
project completion time with the least increase in the cost over normal costs.
e) The
minimum completion time, assuming a budget of $23,500.
f) The
minimum cost to complete the project in 12 weeks.