EMV Problem for Page Engineering
Page Engineering designs and constructs air conditioning and
heating (HVAC) systems for hospitals and clinics. Currently the company’s staff
is overloaded with design work. There is a major design project due in 8 weeks.
The penalty for completing the design late is $14,000 per week, since any delay
will cause the facility to open later than anticipated, and cost the client
significant revenue. If the company uses its inside engineers to complete the
design, it will have to pay them overtime for all work. Page has estimated that
it will cost $12,000 per week (wages and overhead), including late weeks, to
have company engineers complete the design. Page is also considering having an
outside engineering firm do the design. A bid of $92,000 has been received for
the completed design. Yet another option for completing the design is to
conduct a joint design by having a third engineering company complete all
electromechanical components of the design at a cost of $56,600. Page would
then complete the rest of the design and control systems at an estimated cost
of $30,000.
Page has estimated the following probabilities of completing
the project within various time frames when using each of the three options.
Those estimates are shown in the following table:
Probability of Completing the Design
Option On-Time 1 wk. late 2 wks. Late 3
wks. Late
Internal Eng. 0.4 0.5 0.1 ——-
External Eng. 0.2 0.4 0.3 0.1
Joint Design 0.1 0.3 0.4 0.2
What is the best decision based on an expected monetary
value criterion?