WEEK 6: TEAM CASE
ANALYSIS
Installed in 2004 as part of a £200 million IT modernization
of Great Britain’s National Health Service (NHS), the patient booking system
was supposed to enable patients to select a hospital for an outpatient appointment
from a range of options, primarily with the help and direction of their general
practitioner (Laudon & Laudon, 2015, p.547). According to the NHS Alliance, a coalition of
health care providers, managers, and patients dedicated to improving care and providing
a voice to patients, the ability to choose physicians and facilities from a
wide range of options was never a chief concern (Laudon & Laudon, 2015,
p.547). Instead, patients were looking for swift referrals to their local
hospital. In rural areas, choice was considerably limited anyway, and older
patients, in particular, simply found the array of choices confusing, difficult
to navigate, and time-consuming to select (Laudon & Laudon, 2015, p.547).
The goals were threefold: to speed up the referral process, eliminate costly
paperwork, and encourage patient participation so as to stem losses of up to
£225 million annually from 1.6 million patient no-shows (Laudon & Laudon,
2015, p.547).
Support
The NHS
was initiated in 1948. One of the NHS goals is to provide a good healthcare to
everyone, regardless of wealth with the exclusion of some charges, like
prescriptions, visual services and dental services. The NHS in England receive
everyday over 1 million patients every 36 hours.
The NHS Modernization agency work in improving services
through four important elements which are strategic to progress and deliver a
truthfully patient-centered services.
In order to support the speed up to the access of the
patient’s services, the NHS agency also helped each part of the NHS in order to
deliver national waiting and booking targets (Dr. Gill Morgan,2009). The NHS
agency working to familiarize the patient choice and expand emergency care
service.
NHS is also working to provision the local level by
supporting associations and leaders in new roles, through helping them to build
networks and also to work regarding creating a local modernization support
teams, and networks in each community.
NHS works to provide a quick support to under-achieving
parts of the NHS, and encourage practicing in order to meet improvements.
Finally, the NHS is working hard to create an inclusive
library of good backup resources to give agency practical help, learn and share
their understanding and learning.
The NHS agency still need to spend around £600m on CSC’s
Lorenzo patient record system as a legacy of the defunct National Programmer
for IT (NPfIT). (Kathleen Hall,2013)
“You’re going to spend another half billion with the rotten
company to supply hopeless software,” said Margaret Hodge, PASC chair.
(Kathleen Hall,2013).
Evaluation
Companies are always looking for a way to save on time,
resources, and cost. To remain competitive, companies need to investigate on
how to implement information systems projects to improve quality and customer satisfaction.
In most cases, projects take much longer than anticipated or the completed
system does not work properly. When systems do not go according to plan,
companies will not realize the benefits they were originally seeking (Laudon
& Laudon, p 544).
In
2004, Great Britain’s National Health Service installed a system called “Choose
and Book.” Choose and Book was an attempt to help reduce the amounts of
no-shows, speed up the referral process, eliminate costly paperwork, and
encourage patient participation. The system was supposed to help give patients
options to book online to a select hospital for outpatient appointments with
the assistance from their general practitioner. A referral number and security
code would then be generated which would allow a patient to go online or call
to confirm their appointment (Laudon & Laudon, p 547).
Choose
and Book met many challenges. The implementation was slow and was plagued with
many issues and glitches. The two systems the hospital utilized were not
compatible which led programmers to create systems that would streamline both.
The four-year goal to book 90% of all referrals with Choose and Book was not
achieved despite installing systems into 94% GP surgeries. Only 54%
appointments were scheduled using Choose and Book (Laudon & Laudon, p 547).
A study performed by Oxford University and McKinsey, found 33% of projects run
over schedule, 66% over budget, and nearly 17% face multiple issues that it
threatens a company’s future existence (Laudon & Laudon, p 544).
Most
providers embraced the new system; however, due to the multiple issues with the
system, caregivers and patients refused to use Choose and Book. Some of the
issues they faced were last-minute cancellations, errors with appointment
letters, costs incurred for phone calls to the booking line in some locations,
and treatment delays due to lack of urgent and routine visit categorization not
incorporated because cases requiring immediate treatment bypassed the queuing
system (Laudon & Laudon, p 547).
Despite
investing a substantial amount of money to build the system, the project did
not materialize the projected savings they anticipated. Due to the many
glitches they faced, doctors and patients dropped out of using the system. With
the rising costs to fix the multiple glitches, a new system was developed at
the end of 2014 that would replace the hybrid electronic/paper system into an
all-electronic system utilizing e-Referral service with the goal of total
implementation by 2019. The overall goal is to improve upon the Choose and Book
system and eliminate the flaws associated with it (Laudon & Laudon, p
548).
The new system uses a set of application programming
interfaces (APIs) along with an open platform, both of which provide more
flexibility to integrate with other systems. This new system would provide a
less restrictive proprietary system versus Choose and Book. Additionally, these
changes should reduce operating costs (Laudon & Laudon, p 548). In
promoting this new system, project management will be key in organizing,
developing, and implementing the new system. Well thought out strategies are
vital to ensuring users play important roles throughout the planning and
implementation process (Laudon & Laudon, p 560).
1. Clarify and describe the problems of
the NHS Choose and Book System what management, organization and technology
factors were responsible for those problems?
2.
To
what extent was Choose and Book a failure? Explain your answer.
3.
What
was the economic and social impact of Choose and Book?
4.
Describe
the steps that should have been taken to make Choose and Book more successful