Activity Duration Predecessors
A 5 Days —
B 6 Days —
C 8 Days —
D 4 Days A, B
E 3 Days C
F 5 Days D
G 5 Days E, F
H 9 Days D
I 12 Days G
What is the scheduled completion of the project? (5 points)
What is the critical path of the project? (5 points)
What is the ES for activity D?
What is the LS for activity G?
What is the EF for activity B?
What is the LF for activity H?
What is the float for activity I?
Can you show me how you can calculate this problems