To determine a standard time for the task, an employee from an existing assembly station was trained in the new assembly process. Once proficient, the employee was then asked to perform the task 17 times so a standard could be determined. The actual times observed were as follows ( in minutes ) :
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
2.05 1.92 2.01 1.89 1.77 1.80 1.86 1.83 1.93 1.96 1.95 2.05 1.79 1.82 1.85 1.85 1.99
The worker had a 115% performance rating. The task may be performed in a sitting position at a well-designed ergonomic workstation in an air-conditioned facility. Although the armature itself weights 10.5 pounds, there is a carrier that holds it so the operator need only rotate the armature. But, the detail work remains high :â therefore, the fatigue allowance will be 8%. The company has an established personal allowance of 6%. Delay should be very low. Previous studies of delay in this department average 2%. This standard is to use the same figure.
The workday is 7.5 hours, but operators are paid for 8 hours at an average of $12.50 per hour.
Questions
In your report to Ms. Wojdat , you realize you will want to address several factors :
a) how large should the sample be for a statistically accurate standard ( at ,
say, the 99.73 % confidence level and accuracy of 5% ? )
b) is the sample size adequate ?
c) how many units should be produced at this workstation per day ?
e) what is the cost per unit for this task in direct labor cost ?