Comprehensive Variance Analysis for Turner Corporation
several small specialty automobile companies. Prior to founding the firm,
Benson Turner, the company’s president, had an illustrious stock-car-racing
career. After several serious injuries, Benson’s family convinced him that it
was time to retire from the sport and pursue a calmer and safer line of work.
The company has been operating for just over five years and
is beginning to show signs of significant growth. Benson is a planner, and he
wants to get a handle on his manufacturing operations before the company’s
growth becomes his primary preoccupation. The company’s plant manager and
controller met last week to pull together information that they could present
to Benson. Although the company produces over 150 different parts, the two of
them thought that accumulating detailed data on one single typical part would
be sufficient for the quickly called meeting. As a consequence, the following
data were captured for the last 12 months:
– Budgeted
production and sales: 12,000 parts
– Actual
production and sales: 11,000 parts.
– Each
part has a standard requiring 1 pound of material at a budgeted cost of $1.50
per pound.
– Each
part has a standard requiring 20 minutes of assembly time at a cost of $0.25
per minute.
– The
average actual wholesale price for each part is $8.
– Actual
costs for the production of 11,000 parts were ,094 for 11,100 pounds of
material.
– Actual
labor costs were $58,080 for 242,000 minutes of labor time.
A. What was
the actual budgeted contribution margin per part?
B. What was
the actual contribution margin per part?
C. What was
Turner’s flexible budget variance?
D. What was
Turner’s direct material price variance?
E. What was
Turner’s direct material usage variance?
F. What was
Turner’s labor rate variance?
G. What was
Turner’s labor efficiency variance?