You
are a project manager in the IT department of a company. You have been
asked to develop a customised software application for the sales
department of your company. You have already gathered the requirements,
documented the specifications, and developed a project schedule. The
head of the sales department wants the user interface of the software to
be generated early in the project so that she can provide feedback that
will enable you to make adjustments to the user interface. After seeing
the user interface, the head of the sales department suggests a number
of changes and some new features to be added to the software.
On the basis of the project information, complete the following tasks:
- Construct a project schedule to determine the overall cost of and time for the project.
- Identify the finish date.
- Calculate the total cost.
- scribe the process that was followed to review and approve the change request.
- Identify the new finish date after the approval of changes.
- Calculate the new total cost after the approval of changes.
Use the following information for arriving at your answers:
|
Task # |
Description |
Duration |
Predecessor |
|
1 |
Gather requirements |
10 days |
|
|
2 |
Write use cases |
5 days |
1 |
|
3 |
Get client approval |
2 days |
2 |
|
4 |
Write specifications |
5 days |
3 |
|
5 |
Create high-level design |
5 days |
4 |
|
6 |
Create detailed design and schedule |
5 days |
5 |
|
7 |
Create user interface |
15 days |
6 |
|
8 |
Get client feedback |
1 day |
7 |
|
9 |
Create database |
5 days |
6 |
|
10 |
Write support modules |
30 days |
6 |
|
11 |
Unit test support modules |
5 days |
10 |
|
12 |
Write high-level functions |
45 days |
6 |
|
13 |
Unit test high-level functions |
10 days |
12 |
|
14 |
Integration testing |
5 days |
13,11 |
|
15 |
Acceptance testing |
5 days |
14,8 |
Required resources are as follows:
|
Tasks |
Required resources |
|
Gather requirements |
Product manager and project manager |
|
Write use cases |
Project manager and product manager |
|
Get client approval |
Product manager |
|
Write specifications |
Project manager |
|
Create a high-level design |
System architect |
|
Create a detailed design and schedule |
System architect and project manager |
|
Create a user interface |
User interface programmer |
|
Get client feedback |
Project manager and user interface programmer |
|
Create a database |
Database programmer |
|
Write support modules |
Coder |
|
Perform a unit test of support modules |
Coder |
|
Write high-level functions |
Programmer |
|
Perform a unit test of high-level functions |
Programmer |
|
Perform integration testing |
System architect, programmer, and coder |
|
Perform acceptance testing |
Project manager and system architect |
Resource hourly rates (in âŹ/hour) are:
|
Resource |
Hourly Rate |
|
Project manager |
45.00 |
|
Product manager |
40.00 |
|
System architect |
40.00 |
|
User interface programmer |
35.00 |
|
Database programmer |
30.00 |
|
Programmer |
30.00 |
|
Coder |
25.00 |
The
start date for the project is 12 October. All Saturdays and Sundays are
non-working days. Calculate the Saturdays and Sundays on the basis of
the current calendar year. Additionally, the following are non-working
days:
- 30 November
- 25 December
- 28 December
- 1 January
- 4 January
- 17 March
- 2 April
- 5 April
- 3 May
- 31 May
- 12 July
At
the close of the client feedback session (task 8), the head of the
sales department wants some changes to be made, and as such, makes a
formal change request that day. It takes 14 working days for the change
request to be approved.
An analysis of the impact of the change reveals the following:
- Changes to the database module will require 5 days.
- Testing of the new database module will take 5 days following the changes.
- Changes to the support modules will require 7 additional days of work.
- Changes to the high-level functions will require 10 additional days of work.