Week 4 : Project Risk Management – Quiz

Question 1.1. (TCO 1) Which step of the project life cycle
creates the project charter? (Points : 5)

Initiation

Planning

Monitoring and
control

Close out

Question 2.2. (TCO 1) Which document on a project authorizes
the project manager to begin work on the project? (Points : 5)

The scope

The schedule

The charter

The risk
management plan

Question 3.3. (TCO 2) Project deliverables are created in
the _____ , which is completed during the _____ phase of a project. (Points :
5)

charter;
execution

scope;
planning

schedule;
planning

charter;
planning

Question 4.4. (TCO 2) Which statement is an example of a
project constraint? (Points : 5)

“If the parts
arrive late, we will not finish on time.”

“We must get
permits before we start work.”

“I believe the
contracts will be signed by the 15th.”

“The paving of
the parking lot is a major piece of work for this project.”

Question 5.5. (TCO 3) The amount of time an activity can be
delayed without impacting the end date of the project is known as what? (Points
: 5)

Project risk

Slack

Critical path

Early start

Question 6.6. (TCO 3) What values are calculated on the
backward pass of a project network? (Points : 5)

Early start;
late start

Early start;
early finish

Late start;
late finish

Early finish;
late finish

Question 7.7. (TCO 5) In which process of risk management
are proactive and reactive strategies considered? (Points : 5)

Plan risk
management

Plan risk
responses

Control risks

Qualitative
risk analysis

Question 8.8. (TCO 5) Contingency plans are created (Points
: 5)

to proactively
address the risk.

to respond to
the risk should the risk occur.

to gather
information on vital risks.

to avoid red
risks in the project plan .

Week 4 : Project Risk Management – Quiz

Question 1.1. (TCO 1) Before one can begin writing a
charter, one must consider the most appropriate organization for the project.
You are the project manager for an organization that builds doors and windows
for homes. Which organization structure of the five types is most suitable?
Why? (Points : 20)

Question 2.2. (TCO 2) You are reaching the end of your
graduate school program and are planning a large party to celebrate your
success! You have rented out the local forest preserve as the venue for your
party. Applying your project management skills, you want to ensure you have
everything planned out and you’ve asked your family and friends to be a part of
your team to hold this party. At your party, you have made it clear to your
team what you want to have delivered. After all, it’s your party— you can have
whatever you want! Some of the key items you want at your party include

•?????????graduation announcements;

•?????????party invitations;

•?????????live entertainment;

•?????????games (for adults and for
children);

•?????????food;

•?????????beverages; and

•?????????convenience for all (parking,
restroom facilities, etc.).

Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS numbering (15 points).

Part 2: In your WBS, how many work packages have been
created? (5 points) (Points : 20)

Question 3.3. (TCO 3) Compare and contrast fast tracking and
scope reduction as means of schedule compression. (Points : 20)

Question 4.4. (TCO 5) A firm stores data for other
organizations. The company stores data across many states, providing backup
data storage for state, municipal governments, and large corporations. The firm
is deploying a new set of storage devices that are faster, denser, and more
energy efficient.

Part 1: List and discuss the major risk management functions
from a project management perspective for the new data storage project. (15
points)

Part 2: Describe a positive and a negative risk event, the
related consequences, and the risk response plan for each of the two risks for
the new data storage project. (5 points) (Points : 20)

Question 5.5. (TCO 9) Compare and contrast the development
of a WBS in traditional project management versus development in an agile
environment. (Points : 20)

ScholarMatic: Explanation & Answer

Your ready answer from a verified tutor is just a click away for as little as $14.99


  

Click Order Now to get 100% Original Answer Customized to your instructions!

HOME TO CERTIFIED WRITERS

Why Place An Order With Us?

  • Certified Editors
  • 24/7 Customer Support
  • Profesional Research
  • Easy to Use System Interface
  • Student Friendly Pricing

Have a similar question?

PLAGIRAISM FREE PAPERS

All papers we provide are well-researched, properly formatted and cited.

TOP QUALITY

All papers we provide are well-researched, properly formatted and cited.

HIGHLY SECURED

All papers we provide are well-researched, properly formatted and cited.

ScholarMatic: Get Started

Assignment Writing Service

Feel safe and secure when placing an order on our portal!
Fruitful cooperation begins with solid guarantees, and we are professional enough to promise perfect results. Let’s get it started!