Assignment
Requirements
A.
Create a project
schedule: (40 marks)
1.
(20
marks) Develop a work breakdown structure (WBS) for this project.
You can develop this WBS to whatever level of detail
you need, however project reports in this assignment should show 50 to 75 items
(i.e. between 50 and 75 lines in the WBS of any report- Note that this is not a
restriction on the level of detail for your planning but it is a restriction on
the level of detail of your reports).
2.
(20
marks) Based on your WBS for the project, estimate the durations and resources
for the activities that will be required to achieve the project objectives.
Provide a Gantt chart showing the dependencies
between the activities that comprise your project schedule.
Clearly show the resources and durations of the
components of your schedule.
In your schedule, clearly identify the start, end
and duration of the project and the work activities and the dates planned for
any milestones that will need to be achieved to successfully manage the execution
of the project.
B.
Time planning &
control: (20 marks)
1.
(10
marks) The sequence of tasks is based on dependencies, which may be either hard/mandatory
or soft/discretionary. Briefly describe these
different types of dependencies and illustrate both of these with specific examples
taken from your project (Part A).
As a guide, your answer should not be more than 200 words.
- (10 marks) Select one of the effort-driven tasks
in your schedule. Describe how you calculated the duration of that task
(including any method or technique) and the basis for any assumptions made.
As a guide, your answer should not be more than 200
words.
C.
Managing a
Variation: (30 marks)
On the second day after arriving in Europe, your project
is unexpectedly disrupted. Your partner
witnesses a serious crime whilst standing in front of the place in which you
are staying and is subpoenaed to appear in court as a witness for the
prosecution. The court case will
commence on the first Monday after 8 days delay. (The prosecutors require at least 8 days to
prepare evidence and criminal trials always start on a Monday in this country). This case will be heard at the first
opportunity and your partner will be called to give evidence on the first day
of the trial and will not be required after that appearance. However your partner is prevented from
leaving the country until after her trial appearance. You decide to arrange for an additional
week’s leave to compensate for the disruption to the holiday and reorganize
your travel plans to manage these events.
1.
(15 marks) Re-plan your holiday
to include this variation, ensuring that you manage any significant risks associated
with changing and extending the holiday.
Provide a revised WBS and schedule for the project
(with the reports limited to 50 – 75 lines) highlighting any changes made.
2.
(15
marks) Explain the effects of this change on the planned project, including additional
work and activities that have changed or are no longer required.
Explain if and how you can still meet the objectives
of your project within these new constraints on your holiday.
As a guide, this explanation
should not be more than about 350 words.