Lab 7 – Chapter 8: Project Time Management Name:
Chapter 8, Section 1 Exercises
1. A _________ schedule identifies major types of activities and approximate start and end dates for use in decision making about the scope of the project.
2. A schedule of activities that is prepared every two weeks is the _______ schedule.
3. How does a conceptual schedule differ from a master schedule?
Chapter 8, Section 2 Exercises
1. What is work breakdown structure?
2. If two activities are concurrent and they have the same completion date, they have a _______-_______ relationship.
3. A calendar that shows when a person, facility, or key piece of equipment is available is a __________ calendar.
4. What is the advantage of a network diagram over a bar chart for illustrating the critical path?
Chapter 8, Section 3 Exercises
1. The path through the network diagram that has the longest total duration is the __________ path.
2. The difference between the sum of the activity durations along the critical path and the project completion date is the project _______.
3. If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called _________ time.
4. If the last activity in the critical path has a completion date that is five days later than the project completion date, the project has a _______ _________ (two words) of five days.
5. What is the difference between free float and project float?
6. If an activity has a duration of three days, how do you calculate the finish date in a way that considers availability of the resources for that activity?
7. What would be an example of lag time between two activities?
Chapter 8, Section 4 Exercises
1. Accelerating the project schedule is also known as ________ the project.
2. Extra amounts of time and money that are built into the schedule to buffer against delays and extra costs are called…