QSO 600 Operations Management Final Exam

by | Nov 30, 2023 | questions

Problem 1.

Arsenal
Electronics is going to construct a new $1.2 billion semiconductor plant and
has selected four towns in the Midwest as potential sites. The important
location factors and ratings for each town are as follows:

Scores
(0 to 100)

Location Factor

Weight

Abbeton

Bayside

Cane
Creek

Dunnville

Work ethics

0.18

80

90

70

75

Quality of life

0.16

75

85

95

90

Labor laws/unionization

0.12

90

60

60

70

Infrastructure

0.10

60

50

60

70

Education

0.08

80

90

85

95

Labor skill and education

0.07

75

65

70

80

Cost of living

0.06

70

80

85

75

Taxes

0.05

65

70

55

60

Incentive package

0.05

90

95

70

80

Government regulations

0.03

40

50

65

55

Environmental regulations

0.03

65

60

70

80

Transportation

0.03

90

80

95

80

Space for expansion

0.02

90

95

90

90

Urban proximity

0.02

60

90

70

80

Recommend a site based on these location
factors and ratings.

Problem 2.

Sawyer
Furniture is one of the few remaining domestic manufacturers of wood furniture.
In the current competitive environment, cost containment is the key to its
continued survival. Demand for furniture follows a seasonal demand pattern with
increased sales in the summer and fall months, culminating with peak demand in
November.

The cost of
production is $16 per unit for regular production, $24 for overtime, and $33
for subcontracting. Hiring and firing costs are $500 per worker. Inventory
holding costs are $20 per unit per month. There is no beginning inventory. Ten
workers are currently employed. Each worker can produce 50 pieces of furniture
per month. Overtime cannot exceed regular production. Given the following
demand data, use Excel Solver to design an aggregate production plan for Sawyer
Furniture that will meet demand at the lowest possible cost.

Input:

Beg. Wkrs

10

Regular

$16

Hiring

$500

Units/wkr

50

Overtime

$24

Firing

$500

Beg. Inv.

0

Subk

$33

Inventory

$20

Month

Demand

Reg

OT

Subk

Inv

#Wkrs

#Hired

#Fired

Jan

500

500

0

0

0

10

0

0

Feb

500

500

0

0

0

10

0

0

Mar

1000

1,000

0

0

0

20

10

0

Apr

1200

1,000

200

0

0

20

0

0

May

2000

1,000

1,000

0

0

20

0

0

Jun

400

400

0

0

0

8

0

12

Jul

400

400

0

0

0

8

0

0

Aug

1000

1,000

0

0

0

20

12

0

Sep

1000

1,000

0

0

0

20

0

0

Oct

1500

1,500

0

0

0

30

10

0

Nov

7000

3,500

3,500

0

0

70

40

0

Dec

500

500

0

0

0

10

0

60

Total

17,000

12,300

4,700

0

0

246

72

72

Problem 3.

Complete the
following MRP matrix for Item X. Determine when orders should be released and
the size of those orders.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

Net Requirements

Planned Order Receipts

Planned Order Releases

Release
orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50
respectively.

Problem 4.

Fibrous Incorporated makes products from
rough tree fibers. Its product line consists of five items processed through
one of five machines. The machines are not identical, and some products are
better suited to some machines. Given the following production time in
minutes per unit, determine an optimal assignment of product to machine:

Machine

Product

A

B

C

D

E

1

17

10

15

16

20

2

12

?9

16

?9

14

3

11

16

14

15

12

4

14

10

10

18

17

5

13

12

?9

15

11

Problem 5.

The
following probabilistic activity time estimates are for a CPM/PERT network.

Time
Estimates (days)

Time
Estimates (days)

Activity

a

m

b

Activity

a

m

b

1

1

2

?6

?7

1

1.5

2

2

1

3

?5

?8

1

3

5

3

3

5

10

?9

1

1

5

4

3

6

14

10

2

4

9

5

2

4

?9

11

1

2

3

6

2

3

?7

12

1

1

1

Determine
the following:

a.
Expected
activity times

b.
Earliest
start and finish times

c.
Latest start
and finish times

d.
Activity
Slack

e.
Critical
Path

Expected Project duration and standard
deviation.

ScholarMatic: Explanation & Answer

Your ready answer from a verified tutor is just a click away for as little as $14.99


  

Click Order Now to get 100% Original Answer Customized to your instructions!

HOME TO CERTIFIED WRITERS

Why Place An Order With Us?

  • Certified Editors
  • 24/7 Customer Support
  • Profesional Research
  • Easy to Use System Interface
  • Student Friendly Pricing

Have a similar question?

PLAGIRAISM FREE PAPERS

All papers we provide are well-researched, properly formatted and cited.

TOP QUALITY

All papers we provide are well-researched, properly formatted and cited.

HIGHLY SECURED

All papers we provide are well-researched, properly formatted and cited.

ScholarMatic: Get Started

Assignment Writing Service

Feel safe and secure when placing an order on our portal!
Fruitful cooperation begins with solid guarantees, and we are professional enough to promise perfect results. Let’s get it started!