1- Given the following tasks:
|
Task |
Immediate Predecessor |
Duration (weeks) |
|
A |
—- |
6 |
|
B |
A |
3 |
|
C |
A |
7 |
|
D |
C |
2 |
|
E |
B, D |
4 |
|
F |
D |
3 |
|
G |
E, F |
7 |
a.Draw the network.
b.What is the critical path? What is
the completion time?
c.Calculate the total, free, and
safety slack.