Case Study:
Anderson-Touche Consulting Services
Anderson-Touche, an international consulting firm, has just
received a contract from a medium-size manufacturer to install an
Entreprise Resource Planning (ERP) software system. The agreement
includes purchase and installation of a new IBM AS/400 minicomputer
on which to run the massive ERP program. The client manufacturer
desperately needs the new system up and running within 16 weeks so
that its production ability is not endangered. It has included in
Anderson-Touche’s contract a generous bonus for early completion of
the project. It has also included severe penalties for lateness.
Alice Schware, Anderson-Touche’s project manager, wants to make
sure that the installation progresses smoothly and on time. All
activities involved in the ERP project, together with the time
estimates for each activity are shown in the following table:
|
Activity |
Description |
Immediate Predecessor |
Optimistic time |
Most probable time |
Pessimistic time |
|
A B C D E F G H |
Computer hardware delivery Modify new software Install computer Test new software off-site Test new network Training Run new software on new hardware Implement new production system and eliminate old one |
—– —– A B C C D, E F, G |
1 2 1 2 1 1 3 1 |
2 3 2 4 4 2 4 2 |
3 4 3 6 7 9 11 3 |
The project manager asks you to analyze this project. You must
write a managerial report, which should be turned in this afternoon
by 4 p.m.
a)Develop a project network
b)Develop an activity schedule
c)What is the expected completion time
for this project?
d)Identify the critical path and the
non-critical activities?
e)What are the chances of completing
this project within the expected time computed in question c). Why?
Justify your answer
f)What are the chances of completing
this project in the 16-week deadline?
g)What are the chances of completing
this project in 18 weeks? 19 and 21 weeks?
h)If the variance of the project
completion time is the same (does not change) as you found
previously, how much should the expected project completion time be
shortened to achieve the goal of 85% chance of completion within 16
weeks?