Complete the Material Requirements Planning grid below
given the following information:
Beginning inventory = 2
units
Lot Size = 50 units
Lead time = 1 period
| Period | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | |
|
Gross Requirements |
20 | 20 | 40 | 30 | 30 | 30 |
|
Scheduled Receipts |
50 | |||||
|
Projected Available Balance |
||||||
|
Planned Order Receipt |
||||||
|
Planned Order Release |
||||||