Complete the MRP schedule for the product
below.
Product
A Lot
Size = 200
Safety
Stock = 50
Lead Time = 2 weeks
Allocated = 100 In hand =500
WEEKS
|
|
1 |
2 |
3 |
4 |
5 |
|
Gross requirement |
300 |
500 |
800 |
400 |
|
|
Scheduled receipt |
100 |
||||
|
Available |
|||||
|
Net requirements |
|||||
|
Planned order receipts |
|||||
|
Planned order releases |