Create a precedence network using the activity boxes,
not software program. Assume that the ES of activity A is 1. Label
the boxes, develop the relationship lines. Clearly label the
critical path and show the lag times. What is the noraml time shown
on the diagram ?

Show transcribed image text 1. Given the following information: Time Activity Description Normal Predecessor Time Crash Normal Normal Crash Resources $600 $600 A Mobilize 3 1 F, 2 L B i Clearing L IS LA $250 $340 $840 $180 Project 2 S, IL Layout $300 $450 TD Grubbing 1 FA 2 L B 3 $200 $340 Haul and Stockpile Gravel $500 $560 Fill Low $740 Install $700 Underdrain $900 $1000 Place 2 S, L, D, E, F Gravel to 1F Grade $100 $100 3 LIF Pave The greatest number of resources available are 2 F-foremen, 3 S-surveyors, 4L-laborers. All resources are a partial listing only that do not include equipment, specialty crews, etc
1. Given the following information: Time Activity Description Normal Predecessor Time Crash Normal Normal Crash Resources $600 $600 A Mobilize 3 1 F, 2 L B i Clearing L IS LA $250 $340 $840 $180 Project 2 S, IL Layout $300 $450 TD Grubbing 1 FA 2 L B 3 $200 $340 Haul and Stockpile Gravel $500 $560 Fill Low $740 Install $700 Underdrain $900 $1000 Place 2 S, L, D, E, F Gravel to 1F Grade $100 $100 3 LIF Pave The greatest number of resources available are 2 F-foremen, 3 S-surveyors, 4L-laborers. All resources are a partial listing only that do not include equipment, specialty crews, etc