Data Category |
B |
C |
D |
|---|---|---|---|
|
Lot sizing rule |
LFL |
||
|
Lead time |
2 weeks |
1 week |
2 weeks |
|
Scheduled receipts |
100 (week 1) |
0 |
0 |
|
Beginning (onhand) inventory |
0 |
100 |
0 |
The BOM for product A is shown next, and data from the inventory
records are shown in the table. In the master production schedule
for product A, the MPS quantity row (showing completion dates)
calls for 250 units in week 8. The lead time for production of A is
two weeks. Develop the materials requirements plan for the next
eight weeks for Items B, C, and D.