For the questions below, please show your calculation, similar
as the examples discussed in class
1) Use the earned value table for Project Terrace to calculate
their estimated time to completion (all dollar amounts are in
hundreds).

Show transcribed image text Duration in days 9 12 15 Activity Comp o Landscape 100 design 5 Retaining wall 50 2 5 Dirt work 6 10 Move utilities Sprinkler system Planting 12 2 8 14 9 15 Plan 2 10 33 24 48 Cumulative 2 Actual
Duration in days 9 12 15 Activity Comp o Landscape 100 design 5 Retaining wall 50 2 5 Dirt work 6 10 Move utilities Sprinkler system Planting 12 2 8 14 9 15 Plan 2 10 33 24 48 Cumulative 2 Actual