MS Project Problem – Suppose we have a complete
activity predecessor table (shown below). Using MS Project, enter
the activities, their durations and predecessors (use default Fixed
Units).
|
Activity |
Activity Description |
Duration |
Predecessors |
|
A |
Conduct competitive analysis |
3 |
— |
|
B |
Review field sales reports |
2 |
A |
|
C |
Conduct tech capabilities assessment |
5 |
A |
|
D |
Develop focus group data |
2 |
A, B, C |
|
E |
Conduct telephone surveys |
3 |
D |
|
F |
Identify relevant specification improvements |
3 |
E |
|
G |
Interface with marketing staff |
1 |
F |
|
H |
Develop engineering specifications |
5 |
G |
|
I |
Check and debug designs |
4 |
H |
|
J |
Develop testing protocol |
3 |
G |
|
K |
Identify critical performance levels |
2 |
J |
|
L |
Assess and modify product components |
6 |
I, K |
|
M |
Conduct capabilities assessment |
12 |
L |
|
N |
Identify selection criteria |
3 |
M |
|
O |
Develop RFQ (Request for Quote) |
4 |
M |
|
P |
Develop production master schedule |
5 |
N, O |
|
Q |
Collaborate with sales staff |
1 |
P |
|
R |
Prepare product launch |
3 |
Q |
1. Identify the total
Duration:
A) 34 days
B) 55 days
C) 57 days
D) 62 days
2. Identify the Critical
Path:
A) A – (C through I) – L – M – O – P – Q
– R
B) A – (C through I) – L – M – O – Q
C) A – (C through I) – L – M – P – Q
D) A – (C through G) – L – M – O – P – Q
– R
3. If Activity B, Review field
sales reports, takes 7 days to complete instead of the 2 days
estimated, what happens to the total Duration and
why?
A) Total Duration does not change
because slack not totally used up
B) Total Duration does not change
because only used up slack that was available
C) Total Duration increases by 2 days,
because used up 3 days of slack plus 2 additional days
D) Total Duration increases by 2 days,
because of critical path change, slack not overused
4. Assume Activities A through I
are now 100% complete. What is the total project percent
complete?
A) 42%
B) 46%
C) 53%
D) 57%