A=
2
e = 3
Start
B =
5
D =
10
G
= 8
C = 1
F
= 6
Identify the critical path of the network above
|
A-E-G |
||||||||||||||||||||||||||||||||||||||
|
B-D-E-G |
||||||||||||||||||||||||||||||||||||||
|
C-F-G |
||||||||||||||||||||||||||||||||||||||
|
C-F-G and B-D-E-G are both critical Question 4 An activity on a PERT network has these time estimates:
Question 5 A PERT project has 45 activities, 19 of which are on the
|