Objective: |
Completely crash this project. |
||||
|
Activity |
Normal Time |
Crash Time |
Normal Cost |
Crash Cost |
Immediate Predecessor |
|
A |
4 |
3 |
2,000 |
2,600 |
– |
|
B |
2 |
1 |
2,200 |
2,800 |
A |
|
C |
3 |
3 |
500 |
500 |
A |
|
D |
8 |
4 |
2,300 |
2,600 |
A |
|
E |
6 |
3 |
900 |
1,200 |
B, D |
|
F |
3 |
2 |
3,000 |
4,200 |
C, E |
|
G |
4 |
2 |
1,400 |
2,000 |
F |
|
Questions: |
|||||
|
1 |
Complete the AON diagram for this project. |
||||
|
2 |
What is the critical path? |
||||
|
3 |
What is the expected project completion time? |
||||
|
4 |
What is the expected project cost? |
||||
|
5 |
What is the first activity to be crashed? |
||||
|
6 |
What is the crash cost per week for the first activity to be |
||||
|
7 |
What is the minimum project time after completely crashing? |
||||
|
8 |
What is the total crash cost to achieve the shortest project |
Show all necessary calculations in full, carefully labeling the
inputs and the calculated results at each step.
Use only Excel formulas and functions for calculations (ie. do
not type a number that can be calculated by Excel).