Show transcribed image text Problem 14-14 Given the BOM and the MPS for end item A, complete the MRP schedule for items A, C, D, and E. (Leave no cells blank be certain to enter "0" wherever required.) 1 week B (1) C (4 3 weeks 1 week 2 weeks E (2) F (6) E (4) G (4) H (1) 1 week 2 weeks 1 week week 3 weeks MPS Item 60 20 50 120 100 50 80 40 Item A C D E Multiples Lot size rule LAL LAL LAL FOQ 500 Safety stock 100 300 Beginning inventory
Problem 14-14 Given the BOM and the MPS for end item A, complete the MRP schedule for items A, C, D, and E. (Leave no cells blank be certain to enter "0" wherever required.) 1 week B (1) C (4 3 weeks 1 week 2 weeks E (2) F (6) E (4) G (4) H (1) 1 week 2 weeks 1 week week 3 weeks MPS Item 60 20 50 120 100 50 80 40 Item A C D E Multiples Lot size rule LAL LAL LAL FOQ 500 Safety stock 100 300 Beginning inventory