Show transcribed image text Program Evaluation and Review Technique (PERT) Problem A contractor is planning a construction project as shown below Expected/Normal Duration (Days) Cost/Day to Expedite Minimum/Crash Duration (Days) 24 $ 700 12 10 16 800 750 10 14 600 650 The PERT diagram for this project is shown below 2 (22, j4) 3 First, complete filling in both paths in the PERT diagram. Second, identify the critical path for this project by bolding all activities within that path. What is the expected/normal completion time of the project?: What is the minimum/crash completion time for the project?: Show all your work! If there are no calculations to review and the answer is incorrect, then no partial credit can be given
Program Evaluation and Review Technique (PERT) Problem A contractor is planning a construction project as shown below Expected/Normal Duration (Days) Cost/Day to Expedite Minimum/Crash Duration (Days) 24 $ 700 12 10 16 800 750 10 14 600 650 The PERT diagram for this project is shown below 2 (22, j4) 3 First, complete filling in both paths in the PERT diagram. Second, identify the critical path for this project by bolding all activities within that path. What is the expected/normal completion time of the project?: What is the minimum/crash completion time for the project?: Show all your work! If there are no calculations to review and the answer is incorrect, then no partial credit can be given