Question: Reference table: Activity Optimistic Most Likely Pessimistic predecessor A 2 …

by | Nov 30, 2023 | Posted Questions



Reference table:

Activity

Optimistic

Most Likely

Pessimistic

predecessor

A

2

4

8

–

B

2

2

2

–

C

1

5

7

A

D

4

5

6

A

E

3

5

9

C,B

F

1

0

5

C, B

G

2

7

9

C, B

Draw a AON Network with all features:

Calculate the Expected values for all activates, variances, and
the slack (float)

The Critical Path and the Expected completion time (TE)

The probability that the project will be completed in 22
days

The completion time corresponding to a 99% probability

Q 1 AON DIAGRAM

LEDGEND:

ES

EF

Activity, TE, Variance

LS

LF

Q 2

Activity

a

m

b

TE

Variance

Slack (float)

A

2

4

8

B

2

2

2

C

1

5

7

D

4

5

6

E

3

5

9

F

1

0

5

G

2

7

9

Q 3 Critical Path

Q6

CV- Cost Variance. The difference between the earned value and
the actual cost.

SV – Schedule variance. The difference between the earned value
and the planned value.

TV- Time Variance. The difference between time schedule for work
performed and the actual time take for the work performed. Also
represented as:TV= SV/(PV/AT).

CPI – Cost performance index. The ratio of the earned value to
the actual cost.

SPI – Schedule Performance index. The ratio of the earned value
to the planned value.

CSI- Cost Schedule Index. Cost performance index * schedule
performance index.

Q 6 (a- f)

New Concentration project at work the breakdown structure has
the following outlined activities:

Activity

Predecessor

Normal Time (TE) in Days

A: Obtain Instructor

–

7

B: Locate a Room

A

3

C: Check Costs

–

6

D: Room Availability

C

3

E: Schedule Classes

B, D

2

Construct AON network diagram:

Show the ES/EF, LS/LF, and slack for all activities

Show the critical path

Refer to the table below:

Activity

Crash Time (in days)

Crash Cost (total)

Normal Time (TE)

in Days

Normal Cost

(total)

Crash Cost per day

A: Obtain Instructor

4

$ 800

7

$ 500

B: Locate a Room

2

$ 350

3

$ 200

C: Check Costs

4

$ 900

6

$ 500

D: Room Availability

1

$ 500

3

$ 200

E: Schedule Classes

1

$ 550

2

$ 300

Find the crash cost per day for each activity, enter in the
table above.

Which activity should be crashed to meet a project deadline of
10 days (assume partial crashing is allowed for all activities)

Find the new cost.

Q 7:

Project development software is 7 days behind at day 60. Its
planned cost are $830 for this point in time. The actual cost is
$645. Estimate variances to give your answer as to the health of
the project. If the actual cost had been $745, re-estimate the
variance and give you answer to the health of the project.

AC = $645

AC = $745

Day

AC

PV

EV

Day

AC

PV

EV

CV

CV

CPI

CPI

SV

SV

SPI

SPI

CSI

CSI

TV

TV

ScholarMatic: Explanation & Answer

Your ready answer from a verified tutor is just a click away for as little as $14.99


  

Click Order Now to get 100% Original Answer Customized to your instructions!

HOME TO CERTIFIED WRITERS

Why Place An Order With Us?

  • Certified Editors
  • 24/7 Customer Support
  • Profesional Research
  • Easy to Use System Interface
  • Student Friendly Pricing

Have a similar question?

PLAGIRAISM FREE PAPERS

All papers we provide are well-researched, properly formatted and cited.

TOP QUALITY

All papers we provide are well-researched, properly formatted and cited.

HIGHLY SECURED

All papers we provide are well-researched, properly formatted and cited.

ScholarMatic: Get Started

Assignment Writing Service

Feel safe and secure when placing an order on our portal!
Fruitful cooperation begins with solid guarantees, and we are professional enough to promise perfect results. Let’s get it started!