The network below represents a project being analyzed by
Critical Path Methods. Activity durations are
A= 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H =2, I = 10,
and J = 6.
Justify quantitatively your responses to the following
questions:
e) Calculate ES, EF, LS, and LF for each activity.What is slack
time at activity H?
f) What is the Late Finish of activity H?
g) If activity C were delayed by two time units, what would
happen to the project duration?