The PPC system at ABC Company

by | Dec 1, 2023 | Posted Questions

Material
Requirements Planning

The PPC
system at ABC Company is run weekly to update the master production schedule
(MPS) and MRP records.
At the start of week
1, the MPS for end products X and Y is:

Week

1

2

3

4

5

6

Product
X

10

25

5

10

Product
Y

5

30

20

20

One
unit of component C is required to manufacture one unit of either end product X
or Y.
Purchasing lead time for Component
C is two weeks, and order quantity of 40 units is used, and no (zero) safety
stock is maintained for this item.

Inventory balance for component C is 25 units at the start of week 1,
and there’s an open order (scheduled receipt) for 40 units due to be delivered
at the beginning of week 1.

Complete the MRP record for component C as it would
appear
at the beginning of week 1.

Week

1

2

3

4

5

6

Gross
Requirements

Scheduled
Receipts

Projected
Available Balance

Planned
Order Receipts

Planned
Order Releases

During
week 1, the following transactions occurred for component C:

  • The open order for 40 units due to be
    received at the start of week 1 was received on Monday of week 1 with a
    quantity of 35 (5 units of component C were scrapped on this order).
  • An inventory cycle count during week
    1 revealed that ten units of component C were missing.
    Thus, an inventory adjustment of -10 was
    processed.
  • Five units of component C were
    actually disbursed (instead of the 15 units planned for disbursement to
    produce end products X and Y).
    (The
    MPS quantity of 10 in week 1 for product X was canceled as a result of a customer
    order cancellation.)
  • The MPS quantities for week 7 include
    20 units for product X and 10 units for product Y.
  • Because of a change in customer order
    requirements, marketing has requested that the MPS quantity of 5 units for
    product X scheduled in week 4 be moved to week 3.
  • An order for 40 units was released.

Given
this information,
complete the MRP
record
for component C as it would appear at the beginning of week 2:

Week

2

3

4

5

6

7

Gross
Requirements

Scheduled
Receipts

Projected
Available Balance

Planned
Order Receipts

Planned
Order Releases

ScholarMatic: Explanation & Answer

Your ready answer from a verified tutor is just a click away for as little as $14.99


  

Click Order Now to get 100% Original Answer Customized to your instructions!

HOME TO CERTIFIED WRITERS

Why Place An Order With Us?

  • Certified Editors
  • 24/7 Customer Support
  • Profesional Research
  • Easy to Use System Interface
  • Student Friendly Pricing

Have a similar question?

PLAGIRAISM FREE PAPERS

All papers we provide are well-researched, properly formatted and cited.

TOP QUALITY

All papers we provide are well-researched, properly formatted and cited.

HIGHLY SECURED

All papers we provide are well-researched, properly formatted and cited.

ScholarMatic: Get Started

Assignment Writing Service

Feel safe and secure when placing an order on our portal!
Fruitful cooperation begins with solid guarantees, and we are professional enough to promise perfect results. Let’s get it started!